The crane started early on Tuesday November 10th and got the last section (the top) placed on the base and it is all secure. There is still a lot of work remaining before the tower will open to the public but the full height of the tower (110′ at the tip, 100′ at the observation cabin) is together.
A visit today to the fire tower site while setting the course for the Raven Rocks Run (trail race date: Nov 8th) showed some progress and workers on site prepping for some big strides next week.
The fire tower sections are prepped to be assembled together — and they are expecting the CRANE next week to enable the hoisting of “section 3” (aka ‘the middle’) on top of “section 1 & 2” (aka ‘the base’). After that goes well they will get “section 4 & 5” (aka ‘the top’) placed atop sections 1, 2 , & 3.
Once fully assembled, the Cross River Mountain Fire Tower will stand at 100′ high on the exact USGS marker location of the former fire tower (which stood at 60′ high) at this spot.
Fire tower photos from Sunday Sept 6, 2026 plus a triplet of Viscid Violet Cort mushrooms on the trail from the recent rainy weather.
Activity continues at the Fire Tower site as section 3 – the section to the left in the photo of all three sections – is further assembled along with the stairs, railings, and treads.
Much of the activity is happening offsite in the metal shop fabricating and galvanizing new parts for the tower.
Once the third section is complete it will be hoisted atop the portion already set on the foundation.
If you want updates, send a note to firetowerraces@gmail.com with the subject “Tower updates please ;)”
The contractors assembled a wooden scaffolding on top of each section to assist in joining the sections together.
Most recently, section 2 was moved up via crane atop section 1 (the base, which has been anchored to the foundations since November 2025). This structure is now approximately 40′ high.
The stairs, railings, and transition platforms between stair sections are complete in these sections.
In addition, section 5 (the canopy section with the cabin and roof) has been placed on top of section 4 with the help of a wooden scaffolding for safety and ease of working at the joining spots.
This means the work area, which formerly had 4 separate sections of 20′ each now has 2 sections of 40′ each after the combining was finished.
This frees up room on the ground to assemble the middle section – section 3 – which didn’t have enough room in the construction area to be assembled before the combination of section 1 and section 2.
The parts for section 3 have been on-site since 2025 but they were awaiting this moment to get assembled.
Once section 3 is assembled (including stairs, railings, and landings) the big crane will be positioned at the site and it will be lifted atop the foundation sections (section 1 & 2 combined). Shortly after that, the top sections (4 & 5) will be hoisted atop to complete the fire tower.
There are still ground-level items needed before the tower will be officially opened. These include the security fence and the stair cage shown in the concept video. (concept video is here: https://crmfiretower.org/videos/ at about the 2 minute point of the third video listed). Below is a screen shot:
screen shot of concept video showing lower stair cage and security fencing – video source is third video on this page https://crmfiretower.org/videos/
More updates to come as progress is made!
Thank you for your support. Through the Fire Tower Trail Half Marathon & 10k in June we raised over $1,500 in three months from supporters via the Friends of the Fire Tower 501c3.
These funds will go towards educational and accessible exhibits to supplement the tower when it is open. One of the accessible programs we have proposed is a 360° virtual fire tower experience with custom seasonal panoramic views taken from atop our fire tower and available online and also using VR goggles at the Trailside Museum in the park.
We have a new goal of raising $5,000 from now through June 2027 by the NEXT Fire Tower Trail Half Marathon & 10k. We hope you can support us reaching that goal!
Visit to the Cross River Mountain Fire Tower site on Thursday, March 26, 2026 with Taro Ietaka (Ward Pound Ridge Reservation park superintendant), Erika Pierce (Westchester District 2 Legislator), Tom Cohn (Fire Tower volunteer), and Rob Cummings (Fire Tower Volunteer) to check the progress for the project which was recently restarted after the long cold snowy winter atop the mountain.
Four of the five fire tower sections have been assembled. The builders are awaiting the stair risers and treads to install before they can stack them up one by one with a crane (to be delivered when needed).
The fire tower project is expected to be complete during 2026, but the exact date depends on the number of pieces that need to be fabricated for this historic tower.
The county also recently approved a race to raise money for the fire tower: the Fire Tower Half Marathon & 10k Trail Races at Ward Pound Ridge Reservation on June 7, 2026. Registration for both distances is open now at runsignup.com/firetowerraces.
Fire Tower site March 26, 2026Erika Pierce, Tom Cohn, and Taro IetakaFoundation of one corner with the base of the tower attachedFire Tower site March 26, 2026Fire Tower site March 26, 2026Fire Tower site March 26, 2026
As of mid-November 2025 things are moving rapidly on the fire tower restoration.
Several sections have been built at — or moved up to the site of the tower. These sections include the top canopy and the section just below it. They are at the site of the fire tower behind a construction fence right now. The sections have temporary wood frame reinforcements that will help when the crane hoists them up.
The fire tower foundations are underway as well.
Visit https://crmfiretower.org for historic photos of the old fire tower — and information about the new tower and its long-worked for restoration.